あなたを必ず合格させるPMP問題集PDF 2024年最新のに更新されたのは1702問あります [Q328-Q352]

Share

あなたを必ず合格させるPMP問題集PDF 2024年最新のに更新されたのは1702問あります

PMI PMPリアル試験問題と解答を無料で提供いたします


PMI PMP認定は、キャリアを進めたいプロジェクトマネジメントのプロフェッショナルにとって貴重な資格です。PMI PMP(Project Management Professional(2022 Version))認定試験は、現代のビジネス環境でプロジェクトを効果的に管理するために必要な知識とスキルを試す厳しい試験です。適切な準備をすれば、候補者は試験に合格し、キャリア目標を達成することができます。


Project Management Professional(PMP)認定試験は、プロジェクトマネージャー向けの世界的に認められた認定です。これは、プロジェクト管理の分野で最も広く尊敬され、求められている認定の1つです。 PMP認定試験は、プロジェクト管理のトレーニング、教育、認定を提供する非営利組織であるProject Management Institute(PMI)によって提供されます。

 

質問 # 328
The team implemented a risk response plan when a vendor was unable to fulfill a contract commitment for a training class. The response was to choose another vendor. However, in this type of training, it's hard to find a good company, and the one selected doesn't have a much better reputation. The new company is somewhat better at meeting the terms of the contract, but still has some issues from time to time, which is no surprise.
What best describes these issues?

  • A. Residual risk
  • B. Secondary risk
  • C. Risk response plan
  • D. Workaround

正解:A

解説:
Section: Mix Questions


質問 # 329
A project manager is working for an organization in country A and has been tasked with opening the first brick-and-mortar store in country B. The sponsor has identified the city for the store and wants to minimize any potential issues with the local government.
Which action should the project manager take to address the sponsor's request?

  • A. Work with the organization's real estate department and reach out to the local government to identify the best location for the store.
  • B. Work with the organization's legal department to identify local regulations to ensure project compliance.
  • C. Work with the organization's project management office (PMO) to build a project team of residents located in the city.
  • D. Work with the local government to build the profiles of employees that will be working in the store.

正解:B

解説:
The project manager should work with the organization's legal department to identify local regulations to ensure project compliance. This is because the legal department has the expertise to understand and interpret local laws and regulations, which can vary significantly from country to country. By doing so, the project manager can ensure that the project is compliant with local laws, which will minimize potential issues with the local government. References: Project Management Professional (PMP) Reference Materials, PMBOK Guide, Chapter 2: The Environment in Which Projects Operate. Professional in Business Analysis Reference Materials, Chapter 3: Business Analysis Planning and Monitoring.


質問 # 330
The project charter was just approved and the project sponsor has given permission to proceed with the project The program manager has confirmed that one of the requested key resources is also needed on another project at the same time This will affect project delivery What should the project manager do?

  • A. Have a meeting with project manager of the other project to find a resource optimization solution that works for both projects
  • B. Speak with the client to see if the project delivery deadline can be delayed due to resource availability
  • C. Talk to the program manager and about prioritizing this project over other projects so the key resources are available
  • D. Pay overtime to key resource to get the work done outside of working hours

正解:A

解説:
The best option for the project manager in this situation is to have a meeting with the project manager of the other project to find a resource optimization solution that works for both projects. Resource optimization is a technique that aims to balance the demand and supply of resources across multiple projects and ensure that the resources are used efficiently and effectively. By meeting with the other project manager, the project manager can discuss the resource availability, requirements, constraints, and priorities of both projects and explore possible alternatives to resolve the resource conflict. Some of the alternatives may include:
* Sharing the resource between the projects according to a predefined schedule or allocation percentage
* Adjusting the project schedules or activities to reduce the resource overlap or dependency
* Finding another resource with similar skills or qualifications to replace or supplement the requested resource
* Negotiating with the stakeholders to modify the project scope, quality, or budget to accommodate the resource limitation By collaborating with the other project manager, the project manager can find a mutually beneficial solution that minimizes the impact on both projects and maintains a good working relationship with the other project team123. References: = PMBOKGuide, Sixth Edition, pages 318-319, 333-334; Agile Practice Guide, pages
28-29, 50-51; How to Manage Resources Across Multiple Projects.


質問 # 331
A histogram ordered by frequency of occurrence that shows how many results were generated by each identified cause is:

  • A. Fishbone Diagram
  • B. Juran Histogram
  • C. Statistical Histogram
  • D. Pareto Diagram

正解:D


質問 # 332
In which of the following scope management processes is the scope management plan prepared?

  • A. Scope Change Control
  • B. Scope Planning
  • C. Initiation
  • D. Scope definition

正解:B

解説:
Section: (none)
Explanation/Reference:
Your answer choice B is positively correct. Please see PMBOK 2000 Ch.5 Pg 48. I guess
there was an error in the answer choice.
82 http


質問 # 333
A project manager realizes that a new government regulation affects the current project, and to be compliant with the new law, the scope of the project should be changed. The team is now analyzing the impact on the schedule and budget.
Which tool or technique should the project manager have considered before this issue occurred?

  • A. Stakeholder analysis
  • B. Stakeholder register
  • C. Risk register
  • D. Risk management plan

正解:D

解説:
Section: Planning


質問 # 334
A project manager has just been hired to lead a project team in a hybrid environment. The team is working on a group of critical projects.
What should the project manager do to ensure the right environment and authority are in place to effectively deliver the projects?

  • A. Appoint a self-organizing project team that is not influenced by organizational factors.
  • B. Develop a detailed project management plan to share with project resources.
  • C. Develop a detailed risk log and share it with all of the project stakeholders.
  • D. Create a project steering committee aligned with existing organizational structures.

正解:D


質問 # 335
You are the project manager responsible for constructing new 100-unit apartment in downtown Manhattan. As part of construction project, you are planning to outsource the electrical wiring of the building to an outside contracting firm. The contracting firm has requested a statement of work from you. Which of the following statements are FALSE regarding the contract SOW?

  • A. The SOW contains the objectives of the project
  • B. As a buyer, you re required to write SOW
  • C. The outside contracting firm requires a SOW to determine they have the capabilities to meet the detailed specifications of the project
  • D. The SOW is an output of the and acquisitions process and an input to the plan contracting process

正解:B


質問 # 336
If your project is under budget, your cost variance (CV) is:

  • A. Negative
  • B. 0
  • C. Positive
  • D. 1

正解:C


質問 # 337
Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?

  • A. Project Plan
  • B. Issue Log
  • C. Scope Document
  • D. Responsibility Matrix

正解:B

解説:
Section: Monitoring and Controlling


質問 # 338
A business stakeholder for a project is reluctant to accept an agile approach due to a previous bad experience, and is pushing for a predictive approach. What strategy should the project manager use to persuade the stakeholder to use an agile approach?

  • A. Document the request and escalate to upper management to consider a modification of the project charter.
  • B. Agree on a predictive approach, but apply agile concepts under the project management umbrella.
  • C. Propose a phased project approach with multiple small interactions and build trust with the stakeholder through frequent value delivery.
  • D. Ensure the stakeholder that an agile approach will deliver all of the expected results in a shorter period of time.

正解:D


質問 # 339
Deming's Fourteen Points provide a way for an organization to create and sustain a culture of continuous improvement. As such it should be directed by______________

  • A. Employees participating in quality circles
  • B. Top management
  • C. Stakeholders
  • D. The project manager

正解:B

解説:
Explanation/Reference:
Explanation:
Deming is known as a quality pioneer. His approach to quality is not only statistically based but focuses on what management's responsibilities should be with respect to quality. His Fourteen Points for management are goals of quality for transforming business.


質問 # 340
During the execution phase of a healthcare IT project, stakeholders made a change request regarding user requirements There is no remaining budget available to cover that change request.
What should the project manager do next?

  • A. Perform a risk assessment on the required change request.
  • B. Evaluate the change request against the project scope statement
  • C. Discuss approval of the change request in the next project meeting
  • D. Ask the sponsor for more funds to cover the change request

正解:B


質問 # 341
Which of the following is based on an individual identification with a more powerful person.

  • A. expert power
  • B. referent power
  • C. reward power
  • D. expert power and referent power
  • E. expert power and reward power.

正解:B


質問 # 342
An agile team is geographically separated across multiple continents, and the project manager of identifying the tools to manage the communication among the virtual teams Drag the appropriate tool on the left to each project task on the right

正解:

解説:


質問 # 343
The baseline for evaluating whether requests for changes or additional work are contained within or outside the project's exclusion is provided by the______________

  • A. Project scope management plan
  • B. Project scope statement
  • C. Project management plan
  • D. WBS dictionary

正解:B

解説:
Section: Mix Questions
Explanation:
Project exclusion identifies generally what is included within the project, and state explicitly what is excluded from the project, if a stakeholder might assume that a particular product, service, or result could be a project component. Project boundaries are described as part of the detailed project scope statement.


質問 # 344
The cumulative cost curve for planned and actual expenditures______________

  • A. Is also known as a histogram
  • B. Helps to monitor project performance at a glance
  • C. Is used for calculating the CPI
  • D. Forecasts total project expenditures

正解:B

解説:
Section: Mix Questions
Explanation:
Cost curves for planned and actual expenditures are created by adding each month's costs to the previous reporting period's expenditures. By doing so, one can quickly see how the project is performing.


質問 # 345
Despite the project manager's continual reminders about the project's scope, a stakeholder causes frequent disruptions during project status meetings by requesting additional, unplanned activities. What should the project manager do to keep the project on track?

  • A. Update the communications management plan to exclude the stakeholder horn project status meeting
  • B. Add the stakeholder's requests to the change request register as referee
  • C. Ask the stakeholder it they wish to present their requests to the steering committee
  • D. Have the project sponsor educate the stakeholder on the agreed upon project scope

正解:C


質問 # 346
A software system is being built for a company. Once the system is in production, the team would like to collect usage data to evaluate the delivered value.
Which evaluation practice should the project lead use to obtain accurate usage data?

  • A. Build the functionality in the software to collect the operational usage data.
  • B. Embed a feedback form into the system for users to respond.
  • C. Send out a questionnaire to all users regarding the most useful features.
  • D. Interview a sampling of users to obtain the usage data.

正解:A

解説:
Explanation
According to the PMBOK Guide, project monitoring and controlling involves the processes of tracking, reviewing, and regulating the progress and performance of the project. One of the tools and techniques for monitoring and controlling project work is data analysis, which includes methods such as performance reviews, trend analysis, and variance analysis. The project lead should use data analysis to collect and evaluate the operational usage data of the software system, which reflects the actual behavior andpreferences of the users. This will help the project lead to measure the delivered value of the project and identify any gaps or improvement opportunities. Building the functionality in the software to collect the operational usage data is the most accurate and reliable evaluation practice, as it avoids the biases or errors that might arise from other methods such as questionnaires, feedback forms, or interviews. References:
PMBOK Guide, Sixth Edition, Chapter 4: Project Integration Management, pp. 111-158.
PMP Exam Prep Coursebook, Chapter 4: Project Integration Management, pp. 4-1 - 4-24.
Project Evaluation Process: Definition, Methods & Steps by Peter Landau


質問 # 347
Assume that your actual costs are $1,000; your planned value is $1,200; and your earned value is $1,500.
Based on these data, what can be determined regarding your schedule variance?

  • A. At +$300, the situation is favorable, as physical progress is being accomplished ahead of your plan.
  • B. At -$300, the physical progress is being accomplished at a slower rate than is planned, indicating an unfavorable situation.
  • C. At +$500, the situation is favorable, as physical progress is being accomplished at a lower cost than was forecasted.
  • D. At -$300, you have a behind-schedule condition, and your critical path has slipped.

正解:A

解説:
Section: Mix Questions
Explanation:
Schedule variance is calculated as EV - PV, or $1,500 - $1,200 = +$300. Because the SV is positive, physical progress is being accomplished at a faster rate than planned.


質問 # 348
According to the PMBOK Guide, the project manager is identified and assigned during which process?

  • A. At the conclusion of the Develop Project Charter process
  • B. Prior to beginning the Preliminary Scope Statement process
  • C. Prior to beginning the Planning processes
  • D. Prior to beginning the Develop Project Charter process

正解:C

解説:
According to the PMBOK Guide, the project manager should be identified prior to beginning the Planning processes and is named and authorized in the project charter.


質問 # 349
Enterprise environmental factors are an input to which process?

  • A. Collect Requirements
  • B. Control Scope
  • C. Define Scope
  • D. Plan Scope Management

正解:D

解説:
Section: Planning


質問 # 350
When would resource leveling be applied to a schedule model?

  • A. Before it has been analyzed by the critical path method
  • B. After critical activities have been removed from the critical path
  • C. Before constraints have been identified
  • D. After it has been analyzed by the critical path method

正解:D


質問 # 351
An agile project is running activities to define the minimum viable product (MVP). During the session, the project manager identifies some mandatory regulations, but there is no consensus to include these regulations in the MVP because it may extend the duration of the project.
What should the project manager do?

  • A. Train the team on the new regulations as requested by management.
  • B. Ask the project sponsor to add more time to the project.
  • C. Share with the participants the need to focus only on product functionality.
  • D. Get commitment from the team to include all of the required regulations.

正解:D


質問 # 352
......


PMI PMP(Project Management Professional)認定試験は、プロジェクトマネージャー向けの世界的に認められた認定です。認定試験は、プロジェクト管理フレームワーク、プロジェクトの開始、計画、実行、監視、制御、および閉鎖の分野でプロジェクトマネージャーの知識とスキルをテストするように設計されています。 PMI PMP認定試験は、プロジェクト管理認証のゴールドスタンダードとして認識されており、試験に合格すると、プロジェクト管理慣行の習熟度が高いことが示されています。

 