[2025年05月] 合格させるPMP試験一発合格、最新のPMP の提供する試験問題 [Q847-Q872]

Share

[2025年05月] 合格させるPMP試験一発合格、最新のPMP PassTestの提供する試験問題

Project Management Professional問題集でPMP試験の完全版解答試験学習ガイド

質問 # 847
A project manager has just been assigned to a project to build new software for a client. All the requirements have been gathered.
What should the project manager tell the team members to focus on?

  • A. Reducing cost for the customer
  • B. Working together as a team
  • C. Delivering value to the customer
  • D. Finishing the project on schedule

正解:C

解説:
According to the PMBOK Guide, the primary objective of any project is to deliver value to the customer and satisfy their needs and expectations1. The project manager should tell the team members to focus on delivering value to the customer by ensuring that the project deliverables meet the quality standards, the requirements, and the acceptance criteria2. Therefore, the best option is to deliver value to the customer. Option A is incorrect because reducing cost for the customer may not be the main focus of the project, as it may compromise the quality or the scope of the project. Option C is incorrect because working together as a team is important, but it is not the ultimate goal of the project. Option D is incorrect because finishing the project on schedule may not be enough to deliver value to the customer, as it may not reflect the quality or the functionality of the project deliverables. References: 1: PMBOK Guide, 6th edition, section 1.2.2, p. 7 2:
PMBOK Guide, 6th edition, section 5.1.3.1, p. 149


質問 # 848
Present value measures

  • A. the current estimates of our project budget
  • B. the dollars worth of work accomplished as of today
  • C. All of the other alternatives apply.
  • D. the rate of return on an investment when we take account of cash inflows and outflows
  • E. the value to us today of future cash flows.

正解:E


質問 # 849
You are a project manager working on a software development project. You've developed the risk management plan, identified risks, and determined risk responses for the risks. You have recently identified risks in your project and decided to establish a contingency reserve to deal with the risk. The risk response strategy that you used in this scenario is an example of:

  • A. Avoidance
  • B. Mitigateion
  • C. Escalation
  • D. Acceptance

正解:D


質問 # 850
A project for Company A was successfully delivered within scope, schedule, and budget by the end of the last iteration. However, during the project celebration ceremony, one of the business stakeholders says they perceive the project as a failure as it did not add any business value.
What should the project manager have done to avoid this perception?

  • A. Involved the business stakeholders in the sprint review
  • B. Implemented a closing survey for key stakeholders
  • C. Defined product backlog priorities with the sponsor and key stakeholders to deliver business benefits
  • D. Confirmed that there is a communications management plan in place to make business stakeholders aware of the success

正解:C

解説:
Defining product backlog priorities with the sponsor and key stakeholders to deliver business benefits is an important step to ensure that the project is aligned with the business's needs and objectives, and that it delivers the expected value.


質問 # 851
The project has gone smoothly so far. The team members appear to be working with an end goal in mind and without a lot of supervision. They appear highly motivated and enjoying their work.
This is an example of what?

  • A. Motivation Theory
  • B. Reward Theory
  • C. Theory X environment
  • D. Theory Y environment

正解:D


質問 # 852
Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and:

  • A. Enterprise environmental factors
  • B. Project staff assignments
  • C. Interpersonal skills
  • D. Available organizational assets

正解:D


質問 # 853
In which type of organizational structure are staff members grouped by specialty?

  • A. Projectized
  • B. Functional
  • C. Matrix
  • D. Balanced

正解:B


質問 # 854
When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?

  • A. Negative
  • B. Zero
  • C. Positive
  • D. Free

正解:C


質問 # 855
Project Scope Management is primarily concerned with:

  • A. Defining and controlling what is and is not included in the project.
  • B. Determining how requirements will be analyzed, documented, and managed.
  • C. Formalizing acceptance of the completed project deliverables.
  • D. Developing a detailed description of the project and product.

正解:A


質問 # 856
A project manager's team has been expanding in more geographically diverse areas across multiple time zones. Some team members have fast internet connections while others only have certain times they are able to be online. Because of the associations between the tasks, all team members need to be well informed at the same time.
What should the project manager do?

  • A. Set up a project management information system (PMIS)
  • B. Encourage dialogue to ensure there is consistent communication
  • C. Consider access to the Internet as a criteria for team members
  • D. Plan longer retrospectives to ensure all voices on the team are heard

正解:A

解説:
Section: Planning


質問 # 857
A recently concluded quality audit failed and came back with multiple action items. A newly appointed project manager is reviewing the project status with the team. New stakeholders have been identified, and new audit resources may have to be added to the project.
What should the project manager do next?

  • A. Update the risk management plan.
  • B. Update the quality management plan.
  • C. Perform stakeholder engagement.
  • D. Perform integrated change control.

正解:D


質問 # 858
All of the following are true regarding the Quality Planning process except for which one?

  • A. Changes to the product as a result of meeting quality standards might require cost or schedule adjustments.
  • B. The tools and techniques of this process are cost-benefit analysis, benchmarking, DOE, COQ, and additional quality planning tools.
  • C. DOE is a tool and technique of this process that provides statistical analysis for changing product or process elements one at a time to optimize the process.
  • D. This is one of the key processes performed during the Planning process group and during the development of the project management plan.

正解:C

解説:
Design of experiments is a tool and technique of the Quality Planning process that provides statistical analysis for changing key product or process elements all at once (not one at a time) to optimize the process.


質問 # 859
Which activity is an input to the select sellers process?

  • A. Change control process
  • B. Organizational process assets
  • C. Resource availability
  • D. Team performance assessment

正解:B


質問 # 860
The team is working on a critical project deliverable and the project manager is concerned about meeting the deadline. There have been complaints from some stakeholders about some of the team members' performance. The project manager wants to understand the situation and provide feedback to the team as soon as possible.
What three actions should the project manager take to address this situation? (Choose three.)

  • A. Request a manager performance review
  • B. Conduct an annual review
  • C. Implement daily team meetings
  • D. Define team ground rules
  • E. Perform a retrospective session

正解:C、D、E


質問 # 861
You are a contractor for a state agency. Your company recently completed a water resource management project for the state and received payment on its final invoice today. A procurement audit has been conducted. Formal notification that the contract has been closed should be provided to your company by the______________

  • A. Project control officer
  • B. Person responsible for procurement administration
  • C. State's project manager
  • D. Project sponsor or owner

正解:B

解説:
Explanation/Reference:
Explanation:
The person responsible for procurement administration should provide, in writing, formal notification that the contract has been completed. Requirements for formal acceptance and closeout should be defined in the contract.


質問 # 862
Because risk management is relatively new on projects in your company, you decide to examine and document the effectiveness of risk responses in dealing with identified risks and their root causes. You therefore______________

  • A. Reassess identified risks on a periodic basis
  • B. Ensure that risk is an agenda item at regularly scheduled staff meetings
  • C. Conduct a risk audit
  • D. Hold a risk status meeting

正解:C

解説:
Explanation/Reference:
Explanation:
The risk audit is a tool and technique in the control risks process with two purposes: to assess the effectiveness of risk responses and to evaluate the effectiveness of the risk management process.


質問 # 863
Organizational theory is a tool used in which Project Human Resource Management process?

  • A. Acquire Project Team
  • B. Plan Human Resource Management
  • C. Develop Project Team
  • D. Manage Project Team

正解:B


質問 # 864
A project had scheduling delays, which necessitated the team to work overtime to meet critical milestones.
This led to some misunderstandings
among team members. The project sponsor has allocated a monetary award.
How should the project manager utilize the award?

  • A. Meet with the team members and ask them how to spend the reward.
  • B. Arrange a luncheon for all team members and include team-building sessions.
  • C. Draft a points system to allocate a portion of the money for each resource.
  • D. Allocate the reward to the team leaders to spend on the team as they see fit.

正解:B

解説:
In the context of project management, especially after a period of intense work and overtime, it is important to not only reward the team but also to invest in team cohesion and address any misunderstandings that may have arisen. Arranging a luncheon for all team members, coupled with team-building sessions, can serve as both a reward and a means to improve team dynamics. This approach aligns with best practices in project management which emphasize the importance of team development and positive reinforcement12. References:
= Project Management Institute, PMI Professional in Business Analysis.


質問 # 865
Which of the following are the components of the scope baseline?

  • A. Project management plan, plan procurement, and contract administration
  • B. Project charter, project scope statement, and work breakdown structure (WBS)
  • C. Project scope statement, work breakdown structure (WBS), and WBS dictionary
  • D. Project charter, project management plan, and plan procurement

正解:C


質問 # 866
A customer is unhappy after weeks of working in a newly implemented virtual environment and wants their key stakeholders to be more involved in the development processes. The customer is requesting access to the information radiators of the project management information system (PMIS). The development company has never allowed clients access to the system.
What should the project manager do?

  • A. Submit the request and advise for approval, then investigate the training needs for team members and stakeholders.
  • B. Submit the request and advise for denial, as the company has never allowed customers access to the PMIS.
  • C. Break down the request situation to identify the root causes for the customer's dissatisfaction.
  • D. Deny the request and negotiate for alternatives that will achieve the customer's desired results.

正解:C


質問 # 867
The end point of a project phase can be referred to as:

  • A. lifecycle
  • B. stage gate
  • C. project failure
  • D. closing process

正解:B


質問 # 868
The implementation of a business requirement for an IT project impacts several applications. The application owner notices that changes to a function in application X can be started only upon completion of the development of a new feature in application Y.
This is an example of what dependency?

  • A. Start-to-finish (SF)
  • B. Finish-to-start (FS)
  • C. Finish-to-finish (FF)
  • D. Start-to-start (SS)

正解:B

解説:
Section: Executing


質問 # 869
A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.
What should the new project manager do?

  • A. Use a hybrid approach in which agile practices are used but the value is provided to the client at the end of the project.
  • B. Submit a change request to the project board to adjust the delivery date to 2 months earlier than planned.
  • C. Meet with the team to review the backlog and create small iterations that can deliver incremental value to the client,
  • D. Continue working with the predictive approach to deliver the value at the end of the project.

正解:C

解説:
Agile project management emphasizes the delivery of value to the client in small, incremental stages rather than waiting until the end of the project. This approach allows for more flexibility and adaptability, as changes can be made more easily in response to feedback from the client or changes in the project environment.
Therefore, the new project manager should meet with the team to review the backlog and create small iterations that can deliver incremental value to the client. References: Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOKGuide)-Seventh Edition. Project Management Institute.


質問 # 870
A project team member decides to prioritize functional work over allocated tasks for a project. How can the project manager ensure that the project and all tasks will stay on track?

  • A. Meet with the team member's functional manager to suggest including the project task on their performance appraisal.
  • B. Provide the team member with a pay incentive to complete the assigned project work.
  • C. Discuss motivations with the team member to better understand their workload.
  • D. Escalate the team member's noncompliance to their functional manager and request a different resource.

正解:C

解説:
Section: Executing


質問 # 871
_________ is the formal procedure for sanctioning project work to ensure it is done at the right time.

  • A. Project planning
  • B. Work-authorization system
  • C. Status review
  • D. Organizational procedures

正解:B


質問 # 872
......


PMI PMP認定試験は、プロジェクト管理分野の変更を反映するために数年ごとに更新されます。最新バージョンである2023バージョンは、2021年後半にリリースされます。試験の2023バージョンは、アジャイルおよびハイブリッドプロジェクト管理アプローチを含む最新のプロジェクト管理慣行と方法論を反映しています。また、この新しい試験は、プロジェクト管理におけるこれらのスキルの重要性の高まりを反映して、リーダーシップとコミュニケーションスキルにさらに重点を置いています。

 

正真正銘のベスト材料はPMPオンライン練習試験:https://www.passtest.jp/PMI/PMP-shiken.html

最高品質のPMP問題集と解釈が待ってます!今すぐ取得せよ:https://drive.google.com/open?id=1J1ejrXfSUa4lOPlIlSHskXkvhRSVoitm