質問 # 40
Midway through project implementation, stakeholders lose confidence in project management and want to withdraw. What should the project manager use to maintain and improve relationships with the stakeholders?
- A. Pull communication
- B. Power/influence grid evaluation
- C. Interactive communication
- D. Detailed project status reporting
正解:B
質問 # 41
The operations director complains to the CEO about the outcome of a project's first sprint The operations department will not be able to support a new product due to poor performance indicators The project team facilitator asks for feedback from the project team and is informed that performance information is available in the application server log How should this complaint be addressed?
- A. Request that the issue be included in the next board of directors meeting to explain all of the needs
- B. Invite a member of the operations team to be part of the validation and sprint meetings
- C. Ask the operations director to define the acceptance criteria to make clear the delivery is correct
- D. Add the complaint to the product backlog to be addressed in the next sprint
正解:B
質問 # 42
Management reserves are used to handle which type of risk?
- A. business risks
- B. Known unknowns
- C. Unknown unknowns
- D. pure risks
正解:C
質問 # 43
After a functional team delivers a product the project manager uses statistical sampling and inspection to determine if the product performs as expected What is the output of this process?
- A. Quality metrics
- B. Verified deliverables
- C. Quality audit report
- D. Project scope statement
正解:A
質問 # 44
What are the identified risks for doing excessive decomposition in a WBS?
- A. Insufficient project funding and ineffective use of resources
- B. Disqualification of sellers and non-productive management efforts
- C. Insufficient project funding and disqualification of sellers
- D. Non-productive management effort and inefficient use of resources
正解:D
質問 # 45
A company is moving its headquarters to another city. The project manager responsible for the assignment has been using a predictive approach during the transition. However, the information systems will be migrated using an agile approach. The project manager needs to decide which kind of control to sign with the vendor responsible for migrating the systems.
How should the project manager address this situation?
- A. Use fixed-price increments as user stories are completed.
- B. Negotiate payment after all project migration is completed
- C. Confirm payment after each project retrospective
- D. Sign a single agreement for the whole project
正解:A
解説:
When using an agile approach, the project manager should use a contract type that allows for flexibility and adaptation to changing requirements and priorities. A fixed-price contract with increments based on user stories is a suitable option, as it aligns the payment with the delivery of value to the customer. The other options are not appropriate for an agile project, as they either do not provide enough flexibility (A and B) or do not link the payment to the value delivered (D). References: PMBOK Guide, 6th edition, page 374; Agile Practice Guide, page 97.
質問 # 46
An agile project team discovers that they are unable to implement a feature completely in the first iteration The team believes it may not be able to complete the tasks in the second iteration. The feature is a critical component that the customer has prioritized.
What should the team do?
- A. Go back to the customer and explain that they cannot implement the feature completely in one iteration.
- B. Split the feature into smaller subfeatures. implement them, and then deliver them incrementally in multiple iterations
- C. Ask the customer to simplify the feature so that it can be implemented in one iteration
- D. Reduce the scope of the feature to fit into one iteration and deliver it to the customer
正解:B
質問 # 47
You work as a project manager in the largest hospital in the region. Studies have shown that patients have to wait for long periods before being treated. To assist in identifying the factors contributing to this problem, you and your team have decided to use which of the following techniques?
- A. Control charts
- B. Cause-and-effect diagrams
- C. Scatter diagrams
- D. Pareto analysis
正解:B
解説:
Explanation/Reference:
Explanation:
Cause-and-effect diagrams, also called Ishikawa diagrams or fishbone diagrams, are used to illustrate how various causes and subcauses interact to create a special effect. It is named for its developer, Kaoru Ishikawa. These diagrams are useful in linking the undesirable effects seen as special variation to the assigned cause, enabling project teams to implement corrective actions to eliminate the special variation shown in a control chart.
質問 # 48
The primary advantage of using decision-tree analysis in project risk management is that it______________
- A. Considers the attitude of the decision maker toward risk
- B. Helps to identify and postulate risk scenarios for the project
- C. Shows how risks can occur in combination
- D. Forces consideration of the probability of each outcome
正解:D
解説:
Explanation/Reference:
Explanation:
As a graphical way to bring together information, decision-tree analysis quantifies the likelihood of failure and places a value on each decision. Usually applied to cost and time considerations, this form of risk analysis may be linked to a sensitivity analysis.
質問 # 49
Which of the following is an input into the Develop Project Team process?
- A. Performance reports
- B. Project staff assignments
- C. Organizational process assets
- D. Enterprise environmental factors
正解:B
解説:
Section: Executing
質問 # 50
A project manager learns that delays in the design of a ventilation system have caused the project to fall behind schedule The project manager assigns two more engineers to overcome this delay However a week later, they learn that this work package is still lacking progress What should the project manager do?
- A. Assign more engineers.
- B. Issue a change request to revise the schedule
- C. Replace the designers with more experienced ones
- D. Document the issue and brainstorm with subject matter experts (SMEs)
正解:D
質問 # 51
A team has been working together for several months and has successfully delivered work. A new team member has joined the team but is having difficulty contributing.
What should the project manager do to help the new team member integrate effectively?
- A. Review the project with the team member to ensure the project scope is understood
- B. Give the new team member time to contribute until they ask for help and support.
- C. Approach the team member to identify any issues and then plan a resolution accordingly.
- D. Assign the new team member tasks so that the team member knows on what to focus.
正解:C
質問 # 52
Which of the following is not an organizational policy consideration in formulating a project plan?
- A. Quality management
- B. Financial controls
- C. Regulatory compliance
- D. Personnel administration
正解:C
質問 # 53
The project manager is having difficulty communicating with one of the team members The team member recently attended a training course and has been training other team members in a new agile technique However sometimes the team member is forceful in pushing ideas even if other team members are uncomfortable What personality indicators should the project manager consider when determining what communication style to use with this team member?
正解:
解説:
質問 # 54
A project team member has been having a big disagreement with another team member for over two months when the other team members become involved. The issues are complex, but you have specific experience in the area and know what needs to be done. The BEST choice would be to:
- A. Ask the other team members to stay out of the issue.
- B. Make the decision yourself.
- C. Bring the team together and work out the issue to a win-win solution.
- D. Strive for fair resolution of the issue.
正解:D
質問 # 55
A project is initiated to deliver a new version of an existing product. The customer is known for being dissatisfied with the products they receive During the planning meeting, the customer demands that attention be paid to a critical component, as the current version is unusable.
What should the project manager do?
- A. Ensure that a detailed collection of requirements and delivery acceptance criteria are obtained
- B. Validate the requirements traceability matrix
- C. Refer to the stakeholder engagement plan to understand how to interact with this customer
- D. Document the customer's issues and fix them in the new version.
正解:A
質問 # 56
A project has five main sponsors, three of whom often challenge the project manager on the project's status.
What should the project manager do to ensure continuous support from all sponsors?
- A. Meet with the team to set expectations.
- B. Escalate the issue to the project management office (PMO) director.
- C. Meet with the sponsors to understand their expectations.
- D. Document this in the issue log.
正解:C
質問 # 57
The scope management plan and scope baseline are contained in:
- A. the project charter
- B. organizational process assets
- C. the project management plan
- D. a requirements traceability matrix
正解:C
解説:
Section: Planning
質問 # 58
Which of the following best describes the Achievement Theory of motivation?
- A. People are motivated by achievement, power and affiliation
- B. People are motivated by hygiene factors
- C. People are motivated by five basic, hierarchical needs
- D. People are motivated by expectation of positive outcomes
正解:A
質問 # 59
Which statement is false for Constructive changes?
- A. Constructive changes are a frequent cause of disputes and claims of one contract party against the other.
- B. Field changes should be meticulously documented to avoid an interpretation as constructive change.
- C. Constructive changes are contract changes which are construed from actions taken by either party, not from a change document.
- D. Constructive changes are limited to the execution processes, when the product of the project is getting constructed.
正解:D
質問 # 60
Which of the following techniques accounts for path convergence and generally estimates project durations more accurately?
- A. Schedule simulation
- B. PERT
- C. Path convergence method
- D. CPM
正解:A