質問 # 116
An output of the Create WBS process is:
- A. Variance analysis.
- B. Change requests.
- C. Scope baseline.
- D. Accepted deliverables.
正解:C
質問 # 117
A project has the following Earned value data assessed:
AC: $ 4,000,000
CV: $ -500,000 SPI: 1.12 BaC: $ 9,650,000
What is the Earned value of the project?
- A. $5,650,000
- B. $3,500,000
- C. $3,000,000
- D. $4,480,000
正解:B
質問 # 118
As you work on your project to update its software training classes to focus on an agile approach, you have a number of key stakeholders. As many students and their managers are requesting these classes, your CEO has taken a special interest in your project and has asked you to accelerate your schedule to complete it in two months rather than in your planned six months but still have quality offerings. This means as you work to monitor overall project stakeholder relationships, you should______________
- A. Provide presentations to each stakeholder group
- B. Determine how changes will be monitored and controlled
- C. Provide notifications to stakeholders about status regularly
- D. Ask your stakeholders for regular feedback as you work on your project
正解:B
解説:
Section: Mix Questions
Explanation:
As you work in managing stakeholder engagement you should review your project management plan. Your CEO has requested a major schedule change; among other things the project management plan is an input to this process as it contains a change management plan that documents how changes will be monitored and controlled.
質問 # 119
What scope definition technique is used to generate different approaches to execute and perform the work of the project?
- A. Alternatives identification
- B. Build vs. buy
- C. Expert judgment
- D. Product analysis
正解:A
質問 # 120
In an industrial plant, the owner has decided to add more capacity to the plant by installing a new machine and updating the software used in production. This capacity enlargement will occur while the plant is still functioning and producing The software update will be accomplished using an agile approach in order to minimize risk The machine procurement, installation, and integration will be accomplished using predictive approaches What types of communications will the project manager have to design into the schedule management plan to ensure the project will be on schedule''
- A. Biweekly conference calls with the relevant stakeholders
- B. Weekly colocated meetings with the relevant stakeholders
- C. Weekly one-on-one meetings with each of the relevant stakeholders
- D. Biweekly written status reports from the relevant stakeholders
正解:A
質問 # 121
The Project Manager and team are planning the project. They are presently identifying things that could go differently than planned. They are also trying to identify warning signs that would show that these events could be on the verge of occurring. What is the team doing?
- A. Risk analysis
- B. Conformance to quality
- C. Risk Identification
- D. Problem solving
正解:C
質問 # 122
A product implementation project has a baseline schedule that indicates it should be complete within 30 days using three internal resources. As it nears completion, the project manager learns that one resource has left the project team. The sponsor approves hiring an external resource at an additional cost.
To determine if the contingency reserve will be required, what should the project manager calculate?
- A. Variance at completion (VAC)
- B. Budget at completion (BAC)
- C. Cost variance (CV)
- D. Estimate at completion (EAC)
正解:A
解説:
Section: Executing
質問 # 123
As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?
- A. ETC
- B. WBS
- C. BAC
- D. EAC
正解:D
解説:
Section: Initiation
質問 # 124
Due to a company merger and acquisition process, the main stakeholder of a critical project has been changed This new stakeholder complains that they were unaware of a delay on the project of which the rest of the stakeholders were aware. All the communications about the project are shared via email at the start of every week.
How should the project manager address this situation?
- A. Send evidence to the new stakeholder that the project's status was sent according to the schedule
- B. Discuss project requirements with the new stakeholder, and update the communications management plan.
- C. Suggest that the new stakeholder review the project status before the next board meeting
- D. Share the communications management plan with the new stakeholder
正解:B
質問 # 125
During risk analysis for a building renovation project, it is discovered that the building contains toxic materials that must be removed. What should the project manager do to mitigate this risk using the risk transference strategy?
- A. Hire a contractor to perform the work.
- B. Increase the management reserves to address the potential impact of additional time and cost.
- C. Train personnel how to remove the toxic materials and then perform the work.
- D. Ask the client to remove the toxic materials and exclude this work from the contract.
正解:A
解説:
Section: Executing
質問 # 126
A project team is identifying project risks for a bridge to be built across a river. The team needs to send out invitations for a risk workshop to better understand the risks involved.
Which distribution list should the project manager use when sending out invitations?
- A. Weather experts, functional managers, and team members
- B. Functional managers, team members, and external consultants with experience in the field
- C. Team members, engineers, and weather experts
- D. Team members, consultants from outside the project with experience in the field, and the customer
正解:C
質問 # 127
During the execution of an IT project, a project manager warns of the possibility that the main server may fail due to constant, local-area electrical outages. The project manager signs a contract to rent an additional server from a local company.
What strategy is the project manager using?
- A. Enhance
- B. Mitigate
- C. Transfer
- D. Share
正解:B
解説:
Section: Executing
Explanation/Reference:
質問 # 128
In planning your resources for a new building project you are working with an engineering firm, a construction management firm and a general contractor. You are mindful that the general contractor will have to manage several sub-contractors over the next 9 months and that the structural and civil engineers will need to communicate frequently. You must select the best reporting relationships among the parties. This is an example of:
- A. Communication planning
- B. Staffing requirements
- C. Staffing management plan
- D. Project interface planning
正解:D
質問 # 129
When you look at a control chart that measures defects in the product produced by your project, you find that seven values are showing up below the mean on the chart. What should you do?
- A. Ignore the anomaly. This is the rule of seven, so statistically the data doesn't matter.
- B. This means that the mean is too high.
- C. You should adjust your lower control limit - the values indicate a problem with where the limits have been set.
- D. Look into the process that is being measured. There's probably a problem there.
正解:D
解説:
Seven values on one side of the mean in a control chart indicate a problem with the process that is being measured.
質問 # 130
What should you avoid when you are organizing documents as Lessons learned?
- A. Devise the lessons learned documentation in a wording which is easy to understand for a reader who is not familiar with the project.
- B. Writing lessons learned should be an exercise enhancing your personal learning experience. Make sure you grasp what you are writing down.
- C. Keep lessons learned documents at a place where they are easy to access and to retrieve for those who may later need the information.
- D. Lessons learned must detail how certain groups or persons caused failures and delays, especially if they are inside the own organization.
正解:D
質問 # 131
The best way to insure quality conformance is to _____.
- A. train each worker to implement the work.
- B. None of the other alternatives apply .
- C. inspect quality into the project.
- D. distribute the responsibility to subordinates.
- E. maintain total control.
正解:A
質問 # 132
A project manager is closing a project, but can only perform half of the closure activities due to the project's long-term payback period. The project manager should be responsible for which aspects of closure?
- A. Economic strategy
- B. Organizational strategy
- C. Tactical strategy
- D. Business strategy
正解:C
質問 # 133
During the development of a product, multiple identified risks have now become issues, which is hindering the team's velocity. What should the project manager do in this situation?
- A. Prioritize the user stories with issues and have the team resolve them
- B. Update the project management plan and risk management plan.
- C. Convene the steering committee and inform them of the impact to the project.
- D. Document the issues and extend the project delivery timeline.
正解:C
質問 # 134
According to a new product development process, the marketing department will begin adding business and user requirements directly into agile project documents. Drag the product information on the left to the correct documents on the right
正解:
解説:

質問 # 135
......
PMI PMP試験は、PMP認定を獲得したいプロジェクトマネージャーにとって必須の要件です。この試験は、プロジェクトマネジメントの概念、原則、および実践についての候補者の知識をテストするように設計されています。2022年版の試験には、プロジェクトマネジメントの変化に対応した新しい試験内容の概要など、いくつかの更新が予想されています。
PMP問題集PDFで最速合格希望PMP:https://www.passtest.jp/PMI/PMP-shiken.html
100% 高得点合格保証PMP無制限570解答:https://drive.google.com/open?id=12tzJLoItDdxehiXaTPcQBctCRZIr8d5x