質問 # 93
Procurement audits, negotiated settlements, and a records management system are tools and techniques used in which Procurement Management process?
- A. Administer Procurements
- B. Conduct Procurements
- C. Plan Procurements
- D. Close Procurements
正解:D
解説:
Section: Closing
質問 # 94
You are project manager responsible for constructing a new sports arena for the upcoming Olympics. Construction begins on a project over a year ago. The stakeholders of the project want a status report on the performance of the project to date. You've obtained the following measurements:
BAC=500, PV=500, AC=200, EV=300, CPI=1.5
You believe the type of variances that have occurred on the project to date are typical expect these variances to continue throughout the project. Based on the information above, what is the ETC for the project?
- A. 0
- B. 133.33
- C. 1
- D. 2
- E. 333.33
正解:B
質問 # 95
Techniques for Source Selection include all of the following except:
- A. Weighting system
- B. Independent estimates
- C. Screening system
- D. Bidder Conferences
正解:D
質問 # 96
Scope, schedule, and cost parameters are integrated in the:
- A. Performance measurement baseline.
- B. Analysis of past performance.
- C. Analysis of project forecasts,
- D. Summary of changes approved in a period,
正解:A
解説:
Section: Monitoring and Controlling
質問 # 97
Recording and reporting information regarding when appropriate configuration information should be provided and regarding the status of proposed and approved changes effectively is done through______________
- A. Project management methodology
- B. Configuration verification and audit
- C. A project management information system (PMIS)
- D. Configuration status accounting
正解:D
解説:
Section: Mix Questions
Explanation:
Configuration status accounting captures, stores, and accesses the needed configuration information to manage products and product information effectively.
質問 # 98
Project A is critical for the company and must be completed within nine months. The project charter has been signed but the project scope statement has not been prepared. Management asks the project manager to move forward with the project without an approved project scope statement.
What should the project manager do next?
- A. Refuse to work on the project because management is not following standard project management practices
- B. Escalate the issue to the project sponsor and add it to the risk register
- C. Meet with management to explain the potential problems with running a project without a project scope statement
- D. Start the project with inputs from the project charter to save time
正解:C
質問 # 99
A stakeholder requests a change to the project. The project manage wants to avoid wasting the time of the change control board(CCB) and decides to approve the change themselves.
What should the project manager do to make sure they can approvers change?
- A. Request that alt stakeholders vote before making a decision
- B. Review the change with all stakeholders
- C. Obtain the customer's approval before implementation.
- D. Verify that the change does not affect the project baseline
正解:D
質問 # 100
On your project you want to avoid bureaucracy, so you adopt an informal approach to change control. The main problem with this approach is______________.
- A. There are misunderstandings regarding what was agreed upon by stakeholders
- B. Regular disagreements between the project manager and the functional manager will occur
- C. There is a lack of sound cost estimating to assess the change's impact
- D. There is no "paper trail" of change activity
正解:A
解説:
Section: Mix Questions
Explanation:
Using a formal, documented approach to change management reduces the level of misunderstanding or uncertainty regarding the nature of the change and its impact on cost and schedule. For large projects, change control boards are recommended.
質問 # 101
Most schedule simulations are based on some form of which of the following?
- A. CPM
- B. Monte Carlo Analysis
- C. Delphi
- D. PERT
正解:B
質問 # 102
Flextime and compressed workweeks are two popular alternative work schedules used by employers to improve the quality of work life of their employers. Which of the following statements concerning these alternative work schedules is not true?
- A. Flextime schedules alter the employee's working hours but not the number of hours worked each day
- B. Fatigue is a disadvantage of compressed workweek schedules because employees must work longer than the traditional eight hour work day
- C. Both flextime and compressed workweek schedules can complicate compliance with overtime regulations
- D. Both flextime and compressed workweek schedules make scheduling more complex for the employer
- E. Under flextime schedules, the working hours are established by the employer
正解:E
質問 # 103
An output of the Close Project (or Close Phase) process is:
- A. accepted deliverables
- B. project management plan updates
- C. work performance information
- D. organizational process asset updates
正解:D
解説:
Section: Closing
質問 # 104
Which of the following brings together a set of tools and techniques used to describe, organize, and monitor the work of project activities?
- A. Project managers
- B. The PMBOK Guide
- C. Stakeholders
- D. Project management
正解:D
解説:
Project management brings together a set of tools and techniques to organize project activities. Project managers are the ones responsible for managing the project processes.
質問 # 105
When a project is being performed under contract, the SOW is provided by which of the following?
- A. The contractor
- B. The project manager
- C. The project sponsor
- D. The buyer
正解:D
解説:
The buyer provides SOW when projects are performed under contract
Topic 4, Exam 4 (200 questions)
質問 # 106
A vendor project manager and team are implementing a software solution across the organization. A customer stakeholder who was not present during the sales process is demanding that the team implement requirements that are out of scope without adding additional cost to the project.
What should the project manager do next?
- A. Implement all the requirements the customer has requested.
- B. Escalate the issue of the additional requirements to the executive leadership team.
- C. Refer the stakeholder to the delivery specifications in the statement of work (SOW).
- D. Adjust the scope baseline and schedule baseline accordingly.
正解:C
解説:
When a stakeholder demands the implementation of requirements that are out of scope without additional cost, the project manager should refer to the project's statement of work (SOW). The SOW is a formal document that defines the work activities, deliverables, and timeline a vendor will execute for a customer. It serves as a legally binding agreement that specifies what is included in the project scope and, by extension, what is not. If the stakeholder's demands are not included in the SOW, they are considered out of scope, and the project manager should clarify this to the stakeholder. Implementing out-of-scope requirements without adjusting the project's cost, time, and resources can lead to scope creep, which can jeopardize the project's success.
References: The answer is verified with the principles found in the PMI's A Guide to the Project Management Body of Knowledge (PMBOKGuide) and the Professional in Business Analysis Reference Materials provided by PMI12345.
質問 # 107
You are the Project Manager for a company doing research on alternative fuels for automobiles. In your project, which of the following is a valid assumption:
- A. Cost of the project is $ 5 Million
- B. The project scope is to develop alternative fuels only for automobile vehicles weighing less than 10 tons.
- C. The project has to be completed within 2 years
- D. Gasoline fuels will become very expensive and less readily available after 10 years
正解:D
質問 # 108
A construction company is executing a building contract that includes firm milestones for replacing certain components of the building. During execution, the client complains that the new components do not meet the requirements.
What should the project manager have done to prevent this from happening?
- A. Defined acceptance criteria in a quality checklist agreed upon before starting the build phase
- B. Approved a detailed change management process before starting the build phase
- C. Continuously communicated the changes in the work plan and the agreement to the client
- D. Provided compensation for issues due to the variance in the agreed-upon requirements
正解:A
質問 # 109
Which cost is associated with nonconformance?
- A. Liabilities
- B. Equipment
- C. Inspections
- D. Training
正解:A
質問 # 110
A project to implement a new online landing platform has started After the first sprint, the project sponsor requested a change. What should the project manager do next?
- A. Facilitate the update of the product backlog
- B. Validate the work completed
- C. Escalate the change request to the sponsor
- D. Inform the stakeholders of the change
正解:D
質問 # 111
Upon approval, a new project manager immediately begins a project. Three points into me project, the project manager identimes numerous obstacle. What should the project manager have done?
- A. Planned risk responses
- B. Identified risks
- C. Performed a quantitative risk analysis
- D. Performed a qualitative risk analysis
正解:B
質問 # 112
The Perform Integrated Change Control process occurs in which Process Group?
- A. Monitoring and Controlling
- B. Executing
- C. Initiating
- D. Planning
正解:A
質問 # 113
The person in the organization that authorizes the commencement of a project is the
______________?
- A. Project Manager
- B. Senior Manager
- C. Sponsor
- D. Project Admin
正解:C
解説:
The project manager executes the project but does not authorize the project. Sponsor authorize the project.
質問 # 114
You are the project manager for an upcoming outdoor concert event. You're working on the procurement plan for the computer software program that will control the lighting and screen projections during the concert. You're comparing the cost of purchasing a software product to the cost of your company programmers writing a custom software program. You are engaged in which of the following?
- A. Creating the procurement management plan
- B. Make-or-buy analysis
- C. Procurement planning
- D. Using expert judgment
正解:B
解説:
Make-or-buy analysis is determining whether it's more cost effective to purchase the goods or services needed for the project or more cost effective for the organization to produce them internally.
質問 # 115
The following is a network diagram for a project.
The free float for Activity H is how many days?
- A. 0
- B. 1
- C. 2
- D. 3
正解:B
質問 # 116
According to the project contract the delivery date is approaching However one important material is still not on site The construction work will have to stop and wait for this special material, delaying the project.
What should the project manager do?
- A. Record it in the risk register
- B. Ask the client to help solve the problem
- C. Engage the project team to look for alternatives to find a solution
- D. Start procuring this material from another supplier.
正解:C
質問 # 117
......
PMIは最近、2023年1月から有効になる新しいPMP認定試験のリリースを発表しました。更新された試験は、アジャイルやハイブリッドの手法を含む、プロジェクト管理の現在のトレンドと実践を反映します。試験は、単に理論的な知識だけでなく、プロジェクト管理のコンセプトとスキルの実践的な応用に重点を置くようになります。新しいPMP認定試験は、180問の多肢選択問題から構成され、受験者は4時間で試験を完了する必要があります。試験の合格基準は現在の60.6%のままです。試験に合格した受験者はPMP認定を取得し、3年間有効で、継続的なプロフェッショナル開発が必要です。
PMP認定を取得するには、プロジェクト管理における一定の教育と経験の組み合わせを含む特定の資格要件を満たす必要があります。また、180問の多肢選択問題からなるPMP認定試験に合格する必要があり、受験時間は4時間です。この試験はコンピュータベースで、テストセンターまたはオンラインで受験できます。試験に合格した候補者には、3年間有効なPMP認定が授与され、継続的なプロフェッショナル開発が必要です。
テストエンジンに練習PMPテスト問題:https://www.passtest.jp/PMI/PMP-shiken.html
PMPリアル試験問題でテストエンジン問題集トレーニングには1702問あります:https://drive.google.com/open?id=1J1ejrXfSUa4lOPlIlSHskXkvhRSVoitm